Page 245 - RERA Performance Report 2020
P. 245
Project Name : PUSHP KRISHAN PALACE (UPRERAPRJ9708)
District Allahabaad
Promoter Name AMIT GOEL
Project Category Residential
Sanctioning Competent Allahabad Development Authorit
Authority
Start Date 20-05-2017
Original Completion Date 19-05-2019
Revised Completion Date
Validity of Sanction Plan 25-05-2016
Total Towers / Blocks 2
Total Units 72
Completed Towers / Blocks 2
Completed Units 72
Last Quarterly Progress Oct - Dec 2018
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 100
(%)
Date of Completion 11-10-2018
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.