Page 2400 - RERA Performance Report 2020
P. 2400

Project Name : GROUP HOUSING-1(FULL MOON) IN OMAXE
         ETERNITY VIRNDAVAN (UPRERAPRJ2218)

         District                              Mathura

         Promoter Name                         Omaxe Limited
         Project Category                      Residential

         Sanctioning Competent                 Mathura-Vrindavan Development
         Authority
         Start Date                            03-09-2015

         Original Completion Date              31-05-2020
         Revised Completion Date               30-11-2020
         Validity of Sanction Plan             02-09-2020

         Total Towers / Blocks                 1
         Total Units                           114

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 60
         Overall Financial Progress            65
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.