Project Name : EWS (4TH STORY) HOUSES AT RUKMANI
VIHAR AWASIYA YO (UPRERAPRJ11094)
District Mathura
Promoter Name Mathura-Vrindavan Development Authority
Project Category Residential
Sanctioning Competent Mathura-Vrindavan Development
Authority
Start Date 07-10-2009
Original Completion Date 30-11-2016
Revised Completion Date
Validity of Sanction Plan 30-11-2016
Total Towers / Blocks 1
Total Units 672
Completed Towers / Blocks 1
Completed Units 672
Last Quarterly Progress
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 100
(%)
Date of Completion 31-05-2019
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.