Page 2362 - RERA Performance Report 2020
P. 2362

Project Name : BRAJ GANGA RESIDENCY (UPRERAPRJ6546)


         District                              Mathura

         Promoter Name                         BRAJ GANGA RESIDENCY
         Project Category                      Residential

         Sanctioning Competent                 Mathura-Vrindavan Development
         Authority
         Start Date                            15-12-2012

         Original Completion Date              15-12-2018
         Revised Completion Date               14-12-2019
         Validity of Sanction Plan             07-11-2020

         Total Towers / Blocks                 4
         Total Units                           106

         Completed Towers / Blocks             4
         Completed Units                       106

         Last Quarterly Progress               Jul - Sep 2019
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 1, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.