Page 235 - RERA Performance Report 2020
P. 235
Project Name : PRADHAN MANTRI AWAS YOJNA(P.M.A.Y)
(UPRERAPRJ15222)
District Allahabaad
Promoter Name Allahabad Development Authority
Project Category Residential
Sanctioning Competent Allahabad Development Authorit
Authority
Start Date 10-04-2018
Original Completion Date 09-10-2019
Revised Completion Date 29-09-2020
Validity of Sanction Plan 09-10-2019
Total Towers / Blocks 6
Total Units 344
Completed Towers / Blocks 6
Completed Units 344
Last Quarterly Progress Jan - Mar 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 98
Overall Financial Progress 94
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.