Project Name : PMAY (UPRERAPRJ15294)
District Lucknow
Promoter Name U.P. Awas Evam Vikas Parishad
Project Category Residential
Sanctioning Competent U.P. Awas Evam Vikas Parishad
Authority
Start Date 20-02-2018
Original Completion Date 19-12-2019
Revised Completion Date 17-06-2021
Validity of Sanction Plan 20-12-2022
Total Towers / Blocks 1
Total Units 960
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 65
Overall Financial Progress 62
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.