Project Name : CONSTRUCTION OF 480 NOS LIG (G+3)
         HOUSES AT GOKUL (UPRERAPRJ10746)

         District                              Lucknow

         Promoter Name                         U.P. Awas Evam Vikas Parishad
         Project Category                      Residential

         Sanctioning Competent                 U.P. Awas Evam Vikas Parishad
         Authority
         Start Date                            09-03-2015

         Original Completion Date              31-03-2018
         Revised Completion Date
         Validity of Sanction Plan             31-03-2018

         Total Towers / Blocks                 1
         Total Units                           480

         Completed Towers / Blocks             1
         Completed Units                       480

         Last Quarterly Progress               Jan - Mar 2018
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    26-12-2018
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2293   2294   2295   2296   2297   2298   2299   2300   2301   2302   2303