Page 2235 - RERA Performance Report 2020
P. 2235

Project Name : SANJAR GOLD (UPRERAPRJ8807)


         District                              Lucknow

                                               SANJAR BUILDERS AND CONSTRUCTIONS
         Promoter Name
                                               PRIVATE LIMITED
         Project Category                      Commercial

         Sanctioning Competent                 U.P. Awas Evam Vikas Parishad
         Authority
         Start Date                            01-03-2014

         Original Completion Date              31-03-2020
         Revised Completion Date               29-03-2021

         Validity of Sanction Plan             06-04-2021
         Total Towers / Blocks                 1

         Total Units                           169
         Completed Towers / Blocks             0
         Completed Units                       160

         Last Quarterly Progress               Jan - Mar 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 96
         Overall Financial Progress            96
         (%)

         Date of Completion                    Work In Progress
         Certificate

         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   2230   2231   2232   2233   2234   2235   2236   2237   2238   2239   2240