Page 223 - RERA Performance Report 2020
P. 223
Project Name : ALAKNANDA APARTMENT
(UPRERAPRJ12225)
District Allahabaad
Promoter Name Allahabad Development Authority
Project Category Residential
Sanctioning Competent Allahabad Development Authorit
Authority
Start Date 01-10-2014
Original Completion Date 31-12-2019
Revised Completion Date 29-06-2021
Validity of Sanction Plan 30-09-2016
Total Towers / Blocks 4
Total Units 140
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 62
Overall Financial Progress 62
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 6
Orders (Refund + Possession) Refund- 0, Possession- 2
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.