Project Name : AADYANT PHASE-4 (UPRERAPRJ3462)


         District                              Lucknow

         Promoter Name                         Paarth Infrabuild Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Lucknow Development Authority
         Authority
         Start Date                            24-12-2013

         Original Completion Date              31-12-2018
         Revised Completion Date               31-12-2019
         Validity of Sanction Plan             20-06-2021

         Total Towers / Blocks                 1
         Total Units                           5

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Oct - Dec 2019
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 52
         Overall Financial Progress            68
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           1
         Orders (Refund + Possession) Refund- 0, Possession- 1

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2139   2140   2141   2142   2143   2144   2145   2146   2147   2148   2149