Project Name : OZONE CITY PHASE-4 (UPRERAPRJ13504)


         District                              Aligarh

         Promoter Name                         OZONE BUILDERS & DEVELOPERS PVT LIMITED
         Project Category                      Residential

         Sanctioning Competent
         Authority
         Start Date                            15-11-2017

         Original Completion Date              30-11-2020
         Revised Completion Date               29-05-2021
         Validity of Sanction Plan

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   207   208   209   210   211   212   213   214   215   216   217