Page 2069 - RERA Performance Report 2020
P. 2069

Project Name : REVISED GROUP HOUSING GH-1 & GH-2
         ANS INTEGRATED T (UPRERAPRJ4833)

         District                              Lucknow

                                               M/s ANS DEVELOPERS PRIVATE LIMITED(M/s
         Promoter Name
                                               SHALIMAR LAKECITY PRIVATE LIMITED)
         Project Category                      Residential

         Sanctioning Competent                 Lucknow Development Authority
         Authority
         Start Date                            05-02-2016

         Original Completion Date              30-09-2019
         Revised Completion Date               28-03-2021

         Validity of Sanction Plan             20-07-2022
         Total Towers / Blocks                 7

         Total Units                           580
         Completed Towers / Blocks             7
         Completed Units                       580

         Last Quarterly Progress               Apr - Jun 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 100
         Overall Financial Progress            95
         (%)

         Date of Completion                    28-07-2020
         Certificate

         Date of Occupancy Certificate
         Complaints by the Allottees           1
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   2064   2065   2066   2067   2068   2069   2070   2071   2072   2073   2074