Project Name : HARE KRISHNA CITY (UPRERAPRJ13934)
District Kanpur Nagar
Promoter Name HARE KRISHNA DEVELOPERS
Project Category Residential
Sanctioning Competent Kanpur Development Authority
Authority
Start Date 26-10-2017
Original Completion Date 25-10-2025
Revised Completion Date 24-04-2025
Validity of Sanction Plan 25-10-2022
Total Towers / Blocks 5
Total Units 100
Completed Towers / Blocks 0
Completed Units 14
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 19
Overall Financial Progress 24
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.