Page 1650 - RERA Performance Report 2020
P. 1650
Project Name : THE COURTYARD (UPRERAPRJ9460)
District Jhansi
Promoter Name PITAMBARA INFRA PROJECTS LLP
Project Category Residential
Sanctioning Competent Jhansi Development Authority
Authority
Start Date 10-06-2017
Original Completion Date 01-07-2021
Revised Completion Date 29-12-2021
Validity of Sanction Plan 06-03-2020
Total Towers / Blocks 1
Total Units 39
Completed Towers / Blocks 1
Completed Units 36
Last Quarterly Progress Jan - Mar 2018
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 80
Overall Financial Progress 85
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.