Page 1641 - RERA Performance Report 2020
P. 1641
Project Name : DWARIKA (UPRERAPRJ6283)
District Jhansi
Promoter Name Kherapati Buildcon
Project Category Residential
Sanctioning Competent Jhansi Development Authority
Authority
Start Date 02-12-2012
Original Completion Date 31-12-2022
Revised Completion Date 30-06-2023
Validity of Sanction Plan 31-12-2022
Total Towers / Blocks 1
Total Units 173
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 80
Overall Financial Progress 82
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 2
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.