Project Name : VVIP NEST (UPRERAPRJ2675)


         District                              Ghaziabad

         Promoter Name                         Vibhor Vaibhav infrahome Pvt. Ltd.
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            30-03-2015

         Original Completion Date              30-12-2020
         Revised Completion Date               28-09-2020
         Validity of Sanction Plan             29-03-2020

         Total Towers / Blocks                 1
         Total Units                           182

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 25
         Overall Financial Progress            45
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 1, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1550   1551   1552   1553   1554   1555   1556   1557   1558   1559   1560