Page 1520 - RERA Performance Report 2020
P. 1520

Project Name : GANGA, YAMUNA & HINDON ENCLAVE (639
         NOS FLATS) SID (UPRERAPRJ11354)

         District                              Ghaziabad

         Promoter Name                         U.P. Awas Evam Vikas Parishad
         Project Category                      Residential

         Sanctioning Competent                 U.P. Awas Evam Vikas Parishad
         Authority
         Start Date                            12-07-2012

         Original Completion Date              28-02-2019
         Revised Completion Date
         Validity of Sanction Plan             13-08-2017

         Total Towers / Blocks                 12
         Total Units                           1292

         Completed Towers / Blocks             12
         Completed Units                       1292

         Last Quarterly Progress               Apr - Jun 2018
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            97
         (%)

         Date of Completion                    28-02-2019
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 1, Possession- 1

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1515   1516   1517   1518   1519   1520   1521   1522   1523   1524   1525