Project Name : GULMOHAR GARDEN PHASE II
         (UPRERAPRJ3363)

         District                              Ghaziabad

         Promoter Name                         SVP BUILDERS INDIA LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            01-05-2017

         Original Completion Date              31-12-2019
         Revised Completion Date               17-07-2019
         Validity of Sanction Plan             17-07-2018

         Total Towers / Blocks                 13
         Total Units                           1175

         Completed Towers / Blocks             13
         Completed Units                       1175

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 98
         Overall Financial Progress            98
         (%)

         Date of Completion                    06-07-2018,29-12-2018,27-06-2019
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           35
         Orders (Refund + Possession) Refund- 4, Possession- 7

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1494   1495   1496   1497   1498   1499   1500   1501   1502   1503   1504