Project Name : PANCHSHEEL PRIME 390 PHASE -1 (BLOCK 1
         TO 5 & 14 T (UPRERAPRJ8667)

         District                              Ghaziabad

         Promoter Name                         Panchsheel Buildtech Pvt. Ltd.
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            31-10-2016

         Original Completion Date              31-08-2019
         Revised Completion Date               29-12-2020
         Validity of Sanction Plan             22-12-2020

         Total Towers / Blocks                 2
         Total Units                           100

         Completed Towers / Blocks             2
         Completed Units                       100

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    24-06-2020
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1385   1386   1387   1388   1389   1390   1391   1392   1393   1394   1395