Page 1370 - RERA Performance Report 2020
P. 1370
Project Name : OFFICER CITY-2 PHASE-2 (UPRERAPRJ6097)
District Ghaziabad
Promoter Name MR Proview Realtech Private Limited
Project Category Residential
Sanctioning Competent Ghaziabad Development Authorit
Authority
Start Date 01-11-2014
Original Completion Date 05-03-2021
Revised Completion Date 04-09-2021
Validity of Sanction Plan 29-08-2021
Total Towers / Blocks 3
Total Units 45
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR 200000
Overall Physical Progress (%) 24
Overall Financial Progress 24
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 17
Orders (Refund + Possession) Refund- 4, Possession- 9
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.