Page 1364 - RERA Performance Report 2020
P. 1364
Project Name : MILAN EARTH (UPRERAPRJ5373)
District Ghaziabad
Promoter Name Milan Infrastructures And Developers Private Limit
Project Category Residential
Sanctioning Competent Ghaziabad Development Authorit
Authority
Start Date 28-10-2013
Original Completion Date 31-10-2018
Revised Completion Date
Validity of Sanction Plan 28-10-2018
Total Towers / Blocks 1
Total Units 155
Completed Towers / Blocks 1
Completed Units 155
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 95
Overall Financial Progress 70
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 2
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.