Page 1322 - RERA Performance Report 2020
P. 1322
Project Name : 21ST MILESTONE RESIDENCY GHAZIABAD
(UPRERAPRJ8519)
District Ghaziabad
Promoter Name IFCI Infrastructure Development Limited
Project Category Residential
Sanctioning Competent Ghaziabad Development Authorit
Authority
Start Date 17-04-2014
Original Completion Date 20-12-2016
Revised Completion Date
Validity of Sanction Plan 27-12-2017
Total Towers / Blocks 4
Total Units 258
Completed Towers / Blocks 4
Completed Units 258
Last Quarterly Progress
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 100
(%)
Date of Completion 27-12-2017
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 50
Orders (Refund + Possession) Refund- 5, Possession- 4
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.