Page 1300 - RERA Performance Report 2020
P. 1300
Project Name : CONSTRUCTION OF 192 HOUSES AT
POCKET-D INDRAPRASTH YOJANA LONI GHAZIABAD
(UPRERAPRJ440273)
District Ghaziabad
Promoter Name Ghaziabad Development Authority
Project Category Residential
Sanctioning Competent Ghaziabad Development Authorit
Authority
Start Date 16-08-2018
Original Completion Date 15-08-2020
Revised Completion Date 14-08-2021
Validity of Sanction Plan 14-08-2021
Total Towers / Blocks 1
Total Units 192
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 52
Overall Financial Progress 51
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.