Project Name : BHARAT CITY EWS LIG 1 (UPRERAPRJ16752)


         District                              Ghaziabad

         Promoter Name                         BCC INFRASTRUCTURES PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            02-07-2018

         Original Completion Date              02-07-2023
         Revised Completion Date               01-01-2024
         Validity of Sanction Plan             03-01-2023

         Total Towers / Blocks                 1
         Total Units                           491

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 0
         Overall Financial Progress            0
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1253   1254   1255   1256   1257   1258   1259   1260   1261   1262   1263