Project Name : SAVY VILLE DE (UPRERAPRJ10792)


         District                              Ghaziabad

         Promoter Name                         ASCENT BUILDTECH PVT. LTD.
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            01-07-2015

         Original Completion Date              30-12-2020
         Revised Completion Date               29-06-2021
         Validity of Sanction Plan             14-07-2020

         Total Towers / Blocks                 2
         Total Units                           357

         Completed Towers / Blocks             2
         Completed Units                       255

         Last Quarterly Progress               Oct - Dec 2018
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 75
         Overall Financial Progress            70
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           10
         Orders (Refund + Possession) Refund- 3, Possession- 4

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1244   1245   1246   1247   1248   1249   1250   1251   1252   1253   1254