P. 1226
Project Name : INTEGRITY (PHASE - 1: TOWER L & M)
(UPRERAPRJ5025)
District Ghaziabad
Promoter Name AJNARA INDIA LIMITED
Project Category Residential
Sanctioning Competent Ghaziabad Development Authorit
Authority
Start Date 22-12-2015
Original Completion Date 31-12-2018
Revised Completion Date 29-12-2019
Validity of Sanction Plan 22-07-2020
Total Towers / Blocks 2
Total Units 310
Completed Towers / Blocks 2
Completed Units 310
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 84
Overall Financial Progress 77
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 9
Orders (Refund + Possession) Refund- 0, Possession- 4
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.