Page 1198 - RERA Performance Report 2020
P. 1198
Project Name : WTC NOIDA (UPRERAPRJ3504)
District Gautam Buddha Nagar
Promoter Name WTC Noida Development Company Pvt. Ltd.
Project Category Commercial
Sanctioning Competent Greater Noida Authority
Authority
Start Date 20-06-2014
Original Completion Date 31-12-2024
Revised Completion Date 30-06-2025
Validity of Sanction Plan 29-11-2021
Total Towers / Blocks 2
Total Units 5290
Completed Towers / Blocks 1
Completed Units 1488
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 11
Overall Financial Progress 27
(%)
Date of Completion
Certificate
Date of Occupancy Certificate 22-07-2019
Complaints by the Allottees 16
Orders (Refund + Possession) Refund- 1, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.