Project Name : UTC SOFTECH (UPRERAPRJ6886)
District Gautam Buddha Nagar
Promoter Name UTC Softech Private Limited
Project Category Commercial
Sanctioning Competent Noida Authority
Authority
Start Date 30-07-2013
Original Completion Date 30-07-2019
Revised Completion Date
Validity of Sanction Plan 29-07-2018
Total Towers / Blocks 5
Total Units 1691
Completed Towers / Blocks 1
Completed Units 1691
Last Quarterly Progress Jul - Sep 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 100
(%)
Date of Completion 05-03-2020
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 56
Orders (Refund + Possession) Refund- 2, Possession- 10
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.