Page 1090 - RERA Performance Report 2020
P. 1090

Project Name : DELTA CITY CENTRE (UPRERAPRJ10308)


         District                              Gautam Buddha Nagar

         Promoter Name                         STARTLE INFRASTRUCTURE PRIVATE LIMITED
         Project Category                      Commercial

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            10-04-2017

         Original Completion Date              09-10-2019
         Revised Completion Date               07-04-2021
         Validity of Sanction Plan             16-05-2021

         Total Towers / Blocks                 1
         Total Units                           146

         Completed Towers / Blocks             0
         Completed Units                       146

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 95
         Overall Financial Progress            56
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.