Project Name : BEETLE LAP (PHASE II) (UPRERAPRJ7022)


         District                              Gautam Buddha Nagar

                                               ROYAL HOMETOWN PLANNERS PRIVATE
         Promoter Name
                                               LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Yamuna Expressway Authority
         Authority
         Start Date                            21-05-2014

         Original Completion Date              30-06-2019
         Revised Completion Date

         Validity of Sanction Plan             20-05-2019
         Total Towers / Blocks                 1

         Total Units                           236
         Completed Towers / Blocks             1
         Completed Units                       236

         Last Quarterly Progress               Jul - Sep 2019
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 79
         Overall Financial Progress            82
         (%)

         Date of Completion                    Status Not Available
         Certificate

         Date of Occupancy Certificate Status Not Available
         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 0, Possession- 1

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   1036   1037   1038   1039   1040   1041   1042   1043   1044   1045   1046