Project Name : SPEEDWAY AVENUE (UPRERAPRJ12128)


         District                              Gautam Buddha Nagar

         Promoter Name                         PYRAMID TOWNSHIPS PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Yamuna Expressway Authority
         Authority
         Start Date                            01-05-2016

         Original Completion Date              31-12-2022
         Revised Completion Date               21-02-2019
         Validity of Sanction Plan             21-02-2019

         Total Towers / Blocks                 3
         Total Units                           3

         Completed Towers / Blocks             0
         Completed Units                       3

         Last Quarterly Progress               Jul - Sep 2019
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 1
         Overall Financial Progress            1
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1012   1013   1014   1015   1016   1017   1018   1019   1020   1021   1022