Project Name : PRATEEK EDIFICE (UPRERAPRJ2683)


         District                              Gautam Buddha Nagar

                                               PRATEEK INFRAPROJECTS INDIA PRIVATE
         Promoter Name
                                               LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Noida Authority
         Authority
         Start Date                            01-03-2013

         Original Completion Date              30-09-2018
         Revised Completion Date

         Validity of Sanction Plan             22-10-2018
         Total Towers / Blocks                 8

         Total Units                           423
         Completed Towers / Blocks             8
         Completed Units                       423

         Last Quarterly Progress               Oct - Dec 2018
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    29-10-2018
         Certificate

         Date of Occupancy Certificate
         Complaints by the Allottees           12
         Orders (Refund + Possession) Refund- 1, Possession- 1

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   1001   1002   1003   1004   1005   1006   1007   1008   1009   1010   1011